Well, this is the section I've bought. ? :) ? As I said, no mountain or coastal scenery but it is in a pleasant area withing walking distance of the centre of town. ?We could have gone for that 'view', with a couple of hectares even, but that would be some kilometres from town, and that is not what we need.
And the current update? ?Will building soon start? ?No. ? >:( ?I have finally got the drawings completed, the specification finalised, and the contract to look over and sign ...
then it will go to the Council for a couple of months. ?
I did so wonder about the building company's rep's optimism about getting the groundworks done before Christmas. ?Had heard from others that it could take longer than the 6/7 months from start to finish ... maybe for the actual construction of the house but getting the plans and contract ready has taken them far too long. ?It is a good thing we are not on a fixed term rental! ? ? ?
Anyway, the plans show what the house will look like, it's floorplan, where the house is to be built, the drive, areas to be concreted, water tanks etc. and where utilities will spur from. ?The specification sets out practically everything to supplied and be done - down to the last electrical socket, wall tile and carpet bead. ?The Contract sets out the stage payments and all terms and conditions. ?Nothing has been left out. ? ?
I still think I am being treated fairly well. ?They got the 'extras' down by approximately $700 - better than nothing. ?Just hope they are not too busy to get started on the construction when consent has been given. ?:-/ ?